The list of milestones below reflects the milestones to the project to be achieved in time

 

 

 

MS1 Contractual Documents WP1 responsible KIT (due date month 2)

 

Contractual Documents arranged and finished in accordance to the more detailed description edit under task 1.1 (month 2) (OTHER, dissemination level CO, KIT)

 

 

 

MS2 Kick-Off-Meeting WP1 responsible KIT (due date month 2)

 

Kick-Off Meeting (agenda, participant list, project implementation plan, suggestions made and general minutes to the kick-off meeting) (month 2) (OTHER, dissemination level CI, KIT)

 

 

 

MS3 Internal Communication Standards WP1 responsible KIT (due date month 4)

 

Internal Communication Standards (IT-based) arranged and scheduled in accordance to the more detailed description edit under task 1.2. Running website including all project information and its objectives and project technical features needed to exchange information and documents internally included also with invited experts. Share point password protected and all needed documents and information uploaded (month 4) (OTHER, dissemination level PU, KIT)

 

 

 

MS4 Midterm Review WP1 responsible KIT (due date month 21)

 

Midterm Review outcome of midterm review (report of external experts) and incorporation of results to the second half of project task 1.1 (month 20) (OTHER, dissemination level CI, KIT)

 

 

 

MS5 Final Meeting WP1 responsible KIT (due date month 36)

 

Final Meeting (agenda, participant list, project implementation plan, suggestions made and general minutes to the final meeting including further dissemination activities and decisions made on the business concepts to run NET-Tools beyond the project) (month 36) (OTHER, dissemination level CI, KIT)

 

 

 

MS6 LMS Selection WP2 PersEE (due date month 7)

 

LMS Selection including all project information and its objectives and project targets. Decision letter signed by the consortium as a whole to use a very LMS associated with a plan for its technical implementation (month 7, PersEE)

 

 

 

MS7 Launch of NET-Tools WP2 PersEE (due date month 11)

 

Launch of NET-Tools main functionalities including all features needed to exchange information and documents internally also with invited experts (Online connection, navigation and communication through NET-Tools are available) (month 11, PersEE)

 

 

 

MS8 Launch Specific NET-Tools Functionalities WP2 PersEE (due date month 15)

 

Launch of WP3 and WP4 specific functionalities (online access and navigation through e-Courses is available and e-Laboratory is live) (month 15, PersEE)

 

 

 

MS9 Review Technical Concepts and Content e-Laboratory WP3 Ulster (due date month 4)

 

Review of technical concepts and content for e-Laboratory (report on review available on protected area at website) (month 4, Ulster)

 

 

 

MS10 Review Digital Methods and Concepts e-Laboratory WP3 PersEE (due date month 4)

Review of digital methods and concepts for e-Laboratory (report available at the protected area of project website) (month 4, PersEE)

 

 

 

MS11 Database of Stakeholders 1st Version WP3 IEES (due date month 14)

Database of stakeholders for participation in e-Laboratory hands-on-session 1 (database of participants in hands-on-session No.1 is available at the protected area of the project website) (month 14, IEES, contributions by all)

 

 

 

MS12 Database of Stakeholders 2nd Version WP3 IEES (due date month 32)

Database of stakeholders for participation in e-Laboratory hands-on-session 2 (Database of participants in hands-on-session No.2 is available at the protected area of the project website) (month 32, IEES, contributions by all)

 

 

 

MS13 Industrial Safe Case Study WP3 4 - Ulster (due date month 30)

 

Industrial safety case study with the use of HyFOAM from e- Science toolbox (problems formulation document and complete collection of HyFOAM libraries forming the case study to be deposited at the project website) (month 30, Ulster)

 

 

 

MS14 Review Existing Content WP4 UNIPG (due date month 3)

 

Review of existing educational materials and contents performed (list of available information sources and outcome of the review delivered to the Steering committee) (month 3, UNIPG)

 

 

 

MS15 Specification of e-Learning Platform WP4 KIT (due date month 6)

 

Specifications for e-learning platform in place (deliverable D4.2 accepted by WP2 manager and Steering Committee) (month 6, KIT)

 

 

 

MS16 First Courses Online WP4 DTU (due date month 18)

 

First courses online (first courses visible on the project website) (month 18, DTU)

 

 

 

MS17 External Contributions to e-Courses WP4 DTU (due date month 24)

 

First courses set up from outside the consortium (analysis of online courses provided by the platform) (month 24, DTU)

 

 

 

MS18 Concluded and Evaluated WP4 DTU (due date month 30)

 

First courses concluded and evaluated (deliverable D4.5 accepted by the Steering Committee) (month 30, DTU, KIT, Ulster, IEES)